PROPERTY MATTERS
HALL AND CHURCH ROOF RESTORATION
Go To PART 1
Church Preparations
Work in Progress - Week 1

Work in Progress - Week 2
Work in Progress - Week 3
Work in Progress - Week 4
Work in Progress - Week 5

 Go To PART 2
Work in Progress - Week 6
Work in Progress - Week 7
Work in Progress - Week 8
Work in Progress - Week 9

This is PART 3
Work in Progress - Week 10
Work in Progress - Week 11
Work in Progress - Week 12
Work in Progress - Week 13
Work in Progress - Week 14
Work in Progress - Week 15
From January 25th 2009
Upto February 14th 2009
Monday Februray 16th - Saturday February 20th 2009
Monday February 23rd - Saturday February 28th 2009
Monday March 2nd - Saturday March 7th 2009
Monday March 9th - Saturday March 14th 2009
Monday March 16th - Saturday March 21st 2009


From March 23rd 2009
Monday March 23rd - Saturday March  28th 2009
Monday March  31st - Saturday April 5th 2009 [PALM]
Monday April 6th - Saturday April 11th 2009 [EASTER]

Monday April 13th - Saturday April 18th 2009

From April 20th 2009GOTO TOP
Monday April 20th - Saturday April 25th 2009
Monday April 27th - Saturday May 2nd 2009 [MAYDAY]
Monday May 4th - Saturday May 9th 2009
Monday May 11th - Saturday May 16th 2009
Monday May 18th - Saturday May 23rd 2009 [SPRING]
Monday May 25th - Saturday May 30th 2009 [PENTECOST]


Work in Progress - Week 10     Monday April 20th - Saturday April 25th 2009         GOTO TOP

Work in Progress - Week 11           Monday April 27th - Saturday May 2nd              GOTO TOP
back room roof
Finishing off the battens on the back room roof
Wednesday April 29th 2009
back room slated
Slates on the Back room roof
Thursdau April 30th 2009
Back room slated 8-5-09
Back Room clad and slated
May 8th 2009
glimps of cladding
A glimpse of the finish under the protective coat
 Thursday April 30th 2009
Work in Progress - Week 12   Monday May 4th - Saturday May 9th 2009                   GO TO TOP

hall under wrapps
The more or less completed Hall still under wraps
May 8th 2009
kitchen door
A new kitchen door
May 8th 2009
Work in Progress - Week 13         Monday May 11th - Saturday May 16th 2009             GO TO TOP
front of hall reveraled
The wraps come off and reveal the finish
May 16th 2009
taking down the scaffold
The scafolding comes down off the church
May 11th 2009

hall revealed
The south side of the hall revealed
May 16th 2009
back room
The Back Room revealed
May 16th 2009
Work in Progress - Week 14              Monday May 18th - Saturday May 23rd 2009 [SPRING BANK HOLIDASSY]                   GO TO TOP
first pew back
The first pew moveed back by the stewards
May 22nd 2009
BarbaraInQuietGarden_08_07_09
Barbara recovering amidst the lavender in the Quiet Garden
July 8th 2009
GeorgianWay8_7_09
Morning sun on Georgian Way
July 8th 2009
Churchj and Hall 8=7=09
Evening sun on Melbourne Road
July 8th 2009
back_hall_vestry 8/7/09
The 1901 Schoolroom and the reconstructed Back Room
July 8th 2009
Back and side of hall
The north side of the restored hall
July 8th 2009