| PROPERTY MATTERS | ||
| This is PART 1 Church Preparations Work in Progress - Week 1 (Hall roof & cladding) Work in Progress - Week 2 (Hall roof & cladding) Work in Progress - Week 3 (Hall roof & cladding) Work in Progress - Week 4 (Hall roof & cladding) Work in Progress - Week 5 Work in Progress - Week 6 (Stonework and rendering) Go To PART 2 Work in Progress - Week 6 Work in Progress - Week 7 Work in Progress - Week 8 Work in Progress - Week 9 Go To PART 3 Work n Progress - Week 10 Work in Progress - Week 11 Work in Progress - Week 12 Work in Progress - Week 13 Work in Progress - Week 14 Work in Progress - Week 1 5 Work in Progress - Week 1 5 |
From January 25th 2009 Upto February 14th 2009 Monday Februray 16th - Saturday February 20th 2009 Monday February 23rd - Saturday February 28th 2009 Monday March 2nd - Saturday March 7th 2009 Monday March 9th - Saturday March 14th 2009 Monday March 16th - Saturday March 21st 2009 Monday March 23rd - Saturday March 28th 2009 From March 30th 2009 Monday March 23rd - Saturday March 28th 2009 Monday March 31st - Saturday April 5th 2009 [PALM] Monday April 6th - Saturday April 11th 2009 [EASTER] Monday April 13th - Saturday April 18th 2009 From April 20th 2009 |
|
| Church preparations - Upto February 14th 2009 | GOTO TOP | |
The sad exterior of the hall after 83 years use in Llanishen (January 25th 2009) |
The Church Council decides - "Let work begin!" (January 25th 2009) |
|
First objective was to remove the central pews to allow room for the Llanishen Village Nursery to relocate into the church whilst the hall is refurbished. (February 14th 2009) |
Pews were heavy and awkward - successfully carried like the Arc of the Covenant (February 14th 2009) |
|
Operating space for the Llanishen Village Play-Group (displaced from the Hall by the building works) is exposed as the pews were removed (February 14th 2009) |
Pews in storage inside the hall. Neil declares this a "Historic Day" (February 14th 2009) |
|
| Work in Progress - Week 1 Monday Februray 16th - Saturday February 20th 2009 GOTO TOP OF PAGE | ||
On Monday the scaffolding goes up. Monday February 16th 2009 |
Tuesday morning and the roof comes off. Tuesday February 17th 2009 |
|
Boarding and Felting the hall roof Wednesday February 18th 2009 |
The cladding comes off the hall walls. Wednesday February 18th 2009 |
|
Th wall cladding gone from the end wall Wednesday February 18th 2009 |
Ancient wasps nest revealed behind the cladding Saturday February 21st 2009 |
|
Roof felted and battened at the end of Week 1. Saurday February 21st 2009 |
Roof felted and battened at the end of Week 1 Satiurday February 21st 2009 |
|
| Work in Progress - Week 2 Monday February 23rd - Saturday February 28th 2009 GOTO TOP OF PAGE | ||
Roofers pause (above) after removing scaffolding from the end of the roof (right) Monday February 23rd 2009 |
||
Georgian Way side of Hall has all the cladding removed Morning of Wednesday February 25th 2009 |
Removal of brick filler walls (seen also in previous photograph) Added in 1970's to keep out a colony of feral cats Afternoon of Wednesday February 25th 2009 |
|
Georgian Way side of Hall after insulation added Afternoon of Wednesday February 25th 2009 |
Church side of Hall with new sub-cladding started. Brick filler wall removed as noted above. Morning of Wednesday February 25th 2009 |
|
Church side of Hall with sub-cladding completed Afternoon of Wednesday February 25th 2009 |
Welsh slate delivered for hall and church roofs. Afternoon of Wednesday February 25th 2009 |
|
| Work in Progress - Week 3
Monday March 2nd - Saturday March 7th 2009 GOTO TOP |
||
Roofless porch February 27th 2009 |
Remnants of the Back Room of the Hall - for many uears it housed the Primary Department of the Sunday School;; and later the Young Peoples' Fellowship March 1st 2009 |
|
Behind the Church. March 1st 2009 |
Working above the porch roof March 5th 2009 |
|
The roof battened for the slates and a breather membrane covering the sub-cladding March 8th 2009 |
Slates in position on the other side of the Hall roof March 8th 2009 |
|
| Work in Progress - Week 4 Monday March 9th - Saturday March 14th 2009 GOTO TOP | ||
The Llanishen Village Play Group operating in the cleared church and vestry during the work on the Hall. (From the left) Louise Cruse, (5/3/09) Gemma Richards (9/3/09) and Louise Cruse (9/3/09). |
||
A new base for the Hall's Back Rooml March 15th 2009 |
Matching bricks form a new plinth for the Hall itself March 15th 2009 |
|
| Work in Progress - Week 5 Monday March 16th - Saturday March 21st 2009 GOTO TOP | ||
| Work in Progress - Week 6 Monday March 23rd - Saturday March 28th 2009 GOTO TOP | ||
| Continued in PART 2 From March 30th 2009 Continued in PART 3 From May 2nd 2009 |